PROJECT: Bolton Hills
Location: Westminster, MD
Start Date: 2009
Completion Date:
For this residential multiphase development being constructed in Westminster, C.J. Miller is clearing 12 acres, completing 200,000 cubic yards of mass excavation, installing 4,700 linear feet of storm drain, 4, 500 linear feet of waterline, and 5,100 linear feet of sanitary sewer. In addition, 7,000 linear feet of curb is being installed and 3,100 tons of asphalt will be utilized for paving. In this video, workers are completing phases 1 & 2, which includes performing cut-fill operation and storm drain installation.