Townhome and Single-Family Home Development.
72 acres of clearing and over 800k CY of mass grading.
During construction we also installed a single span Contech bridge and 3,800 LF of sewer outfall
LOCATION: New Market, MD
DURATION:
SITE DEVELOPMENT SERVICES
Creekside Hamptons East (New Market, MD)
The Creekside Hamptons East development in New Market, Maryland is a largescale residential project featuring both townhomes and singlefamily homes. CJ Miller is responsible for significant site development across the 72acre property, including full clearing operations and more than 800,000 cubic yards of mass grading.
As part of early infrastructure work, the team installed a singlespan Contech bridge and constructed approximately 3,800 linear feet of sewer outfall. Current efforts focus on roadway and entrance improvements along Gas House Pike, including the installation of a new traffic circle designed to enhance intersection safety and traffic flow.
Upcoming work for Phase 1 includes fine grading of all community roadways, installation of over 12,000 linear feet of curb, and placement of more than 12,000 tons of paving to support the neighborhood’s buildout.
Major Early Infrastructure:
- Installation of a singlespan Contech bridge
- Construction of 3,800 linear feet of sewer outfall
Current Work:
- Entrance and roadway upgrades along Gas House Pike
- Installation of a traffic circle to improve safety and traffic flow
Upcoming Phase 1 Work:
- Roadway fine grading
- 12,000+ LF of curb installation
- 12,000+ tons of paving for community roads